Project Health
Contract Value
$33,846
Original + approved COs
Margin / Profit
$2.22
Revised margin: –$236.67
Claimed to Date
$17,001
50.2% of contract
Cash Received
$0
Cash position: –$100
Budget Remaining (Labour)
–18h
18h over budget
Project Info
Edit
ClientClient 3
Project ManagerAPI User
CategoryMajor Works
Start DateMar 3, 2026
Due DateApr 30, 2026
Deposit$17,000
Retainage5%
Scope of Work
Edit
Supply and commission fire alarm system (2 zones), WC alarm, CCTV with 180° cameras, fire door monitoring, induction loop system, and door entry intercom — all designed as standalone, independent systems with no network interconnection. PPM included for all systems.
Read more →
Activity
+ Add Note
Scope of work updated
Mar 4, 2026 · Uptick Support
SQ-1104 linked to project
Feb 6, 2026 · Uptick Support
Project created
Feb 4, 2026 · Uptick Support
⚡ Needs Attention
3 items
3 time cards pending approval
J. Smith, A. Chen, M. Torres — 4h 22m total
📋
2 change orders awaiting client approval
CO-001 ($4,200) · CO-002 ($1,800) — total $6,000
💰
Pay Application #1 unpaid
$17,001 submitted — 22 days outstanding
Change Orders
2 pending + New
Ref Description Value Status
Extra fire door $4,200 Pending
CCTV expansion $1,800 Pending
Induction loop add $2,100 Approved
Approved total $2,100
Billing Progress
+ New Pay App
$17,001 of $33,846 50.2%
Paid $0
Approved $17k
Submitted $2.8k
Remaining $16.8k
Schedule of Values
Task / Section Total Value Claimed This App. Remaining
Fire Alarm System $12,000 $8,000 $2,000 $2,000
CCTV & Security $9,846 $5,001 $800 $4,045
Intercom & Access $7,200 $4,000 $0 $3,200
Fire Door Monitoring $4,800 $0 $0 $4,800
Time Cards & Labour
By Technician
By Task
3 pending
18h 0m
Total Logged
12h 38m
Budgeted Onsite
–5h 22m
Over Budget
4h 22m
Pending Approval
Technician Task Date Hours Status
J. Smith Mar 16 3h 22m Pending Approve
A. Chen Mar 15 1h 0m Pending Approve
M. Torres Mar 15 0h 0m Pending Approve
M. Torres Mar 14 6h 0m Approved
J. Smith Mar 12 7h 38m Approved
Cost Breakdown
Click a bar to see transactions
Labour
$1,450 actual $1,450 quoted
Materials
$2,179 actual $2,129 quoted +$50 ↑
Subcontracted
$21,060 actual $21,060 quoted
Expenses
–$335 actual $0 quoted ↓ credit
Total cost $24,354 Left to incur: $24,629